LDI Constructions - Subdivisions

LDI Constructions - Subdivisions

Work with private and public clients, on projects large and small, across the region, state and country. Contact us today.

LDI - Cairns' Leading Civil Construction Company

LDI - Cairns' Leading Civil Construction Company

Skilled and experienced team, delivering the highest quality work, on time and on budget, every time. Work as contractor and/or sub-contractor. Extensive project experience on contracts from $100,000 to $70 million.

LDI Constructions - Roadworks

LDI Constructions - Roadworks

We use the latest GPS, Trimble and laser technology. Plant and people. Efficient, effective and quality work. Dynamic solutions to meet your road construction requirements.

Georgetown – NDRRA/TNRP Road Reconstruction and Widening – 2012/13

Project Description

Over 100,000m3 of excavation, pre-splitting of rock batters, installation of culverts, kerb and channel, subsoils, installation of over 30,000m3 of unbound pavement, cement stabilising. Primer seal to over 140,000m2 of new pavement.

Job Specific Challenges

  • The remoteness of the project sites meant freight and transport logistics had to be well thought through to ensure timely delivery of materials and machinery.
  • Job sites were scattered across a 60km distance where mobile coverage was unavailable, therefore communication between sites and the office was limited.
  • Construction water was scarce and the ongoing drought worsened this situation.
  • Job was constructed under traffic with a number of specific requirements regarding lane closures around public holidays.

Project Details

Job NumberQLD Department of Transport and Main Roads (Contract No. PEND/1324)
Duration18 Months
Value$26 Million
Info SheetDownload Information Sheet (PDF)
Resources

Project Manager, 2 x Project Engineers (CQR), Project Supervisor, 3x Foremen, Traffic controllers, Spray seal and asphalt paving crews, Drill and Blast Crew, Remote camp staff, Graders, Excavators (equipped with rock breakers), Stabiliser, Loaders, Water carts, various specialist sub-contractors, Total workforce of 60 personnel.